Title: GB-Loch Striven: Replacement Transfer Pumping Arrangement - OFD Loch Striven - F44 Installation & F76 Strip Out
Notice type: Competitive Contract Notice
Authority: The Oil and Pipelines Agency
Nature of contract: Not applicable
Procedure: Not applicable
Short Description: At present the OFD Loch Striven does not have an F76 fuel filtering system on site and the present pumping system requires the use of the Balance Tank. However, the Balance Tank has been removed from service and decommissioned rendering the existing F76 transfer pumps obsolete. In order to increase the flexibility of the site, there is a requirement to pump between tanks to allow for the complete inter-tank transfers of certain storage tanks. There is also a future requirement to filter off-specification F-76 fuel to allow re-use. In addition, there is a requirement to replace the current F-44 pumps, control systems and power feeds. Power feeds are to be rated IAW with the Depot DSEAR Assessment. The new pump system and filter system will be composed essentially of following: •2 x pumps located in the old Boiler House area •2 x Coalescer Filters (to clean F-76) •2 x new motors and pumps to replace the current aged F44 system. •Associated pipework •Power, control and safety trip systems.
Published: 07/11/2018 15:12
Please note that the deadline for response to this opportunity has passed. However, you can still register or log-into the Delta eSourcing solution to prepare your Supplier Profile for future opportunities.

View Full Notice

Competitive Contract Notice

1. Title: GB-Loch Striven: Replacement Transfer Pumping Arrangement - OFD Loch Striven - F44 Installation & F76 Strip Out
2. Awarding Authority:
    The Oil and Pipelines Agency
    Clive House, 6th Floor, 70 Petty France, Westminster, London, SW1H 9EX, United Kingdom
    Tel. 07891 710312, Email: karen.robinson@oilandpipelines.com, URL: https://gov.uk/opa
    Contact: Karen Robinson, Attn: Karen Robinson
3. Contract Type: Works
      Sub Type: Design and Execution

4. Description: Pumping station construction work. At present the OFD Loch Striven does not have an F76 fuel filtering system on site and the present pumping system requires the use of the Balance Tank. However, the Balance Tank has been removed from service and decommissioned rendering the existing F76 transfer pumps obsolete.
In order to increase the flexibility of the site, there is a requirement to pump between tanks to allow for the complete inter-tank transfers of certain storage tanks. There is also a future requirement to filter off-specification F-76 fuel to allow re-use.
In addition, there is a requirement to replace the current F-44 pumps, control systems and power feeds.
Power feeds are to be rated IAW with the Depot DSEAR Assessment.

The new pump system and filter system will be composed essentially of following:
•2 x pumps located in the old Boiler House area
•2 x Coalescer Filters (to clean F-76)
•2 x new motors and pumps to replace the current aged F44 system.
•Associated pipework
•Power, control and safety trip systems.
5. CPV Codes:
   45232152 - Pumping station construction work.

6. NUTS Codes :
   UK - UNITED KINGDOM

7. Main Site or Location of Works, Main Place of Delivery or Main Place of Performance: UNITED KINGDOM,
8. Reference Attributed by the Awarding Authority:
9. Estimated Value of Requirement: Category G: 500K to 1M
Currency: GBP
10. Deadline for Expression of Interest: 18/12/2018 12:00:00
11. Address to which they must be sent:
    The Oil and Pipelines Agency
    Clive House, 6th Floor, 70 Petty France, Westminster, London, SW1H 9EX, United Kingdom
    Tel. 07891 710312, Email: karen.robinson@oilandpipelines.com, URL: https://gov.uk/opa
    Contact: Karen Robinson, Attn: Karen Robinson
   
12. Other Information:
Other Information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.
For more information about this opportunity, please visit the Delta eSourcing portal at:
https://opa.delta-esourcing.com/tenders/UK-GB-Loch-Striven:-Replacement-Transfer-Pumping-Arrangement---OFD-Loch-Striven---F44-Installation-%26-F76-Strip-Out/3Y464X27BN

To respond to this opportunity, please click here:
https://opa.delta-esourcing.com/respond/3Y464X27BN
TKR-2018117-PRO-13512815
Suitable for VCO: No
Procedure Type:OPEN
Period of Work Start date: 04/03/2019
Period of Work End date: 05/08/2019
Is this a Framework Agreement?: no

View any Notice Addenda

GB-Loch Striven: Replacement Transfer Pumping Arrangement - OFD Loch Striven - F44 Installation & F76 Strip Out

Competitive Contract Notice Addendum

Associated Parent Notice
CompetitiveContractNotice - GB-Loch Striven: Replacement Transfer Pumping Arrangement - OFD Loch Striven - F44 Installation & F76 Strip Out
1. Title: GB-Loch Striven: Replacement Transfer Pumping Arrangement - OFD Loch Striven - F44 Installation & F76 Strip Out
2. Awarding Authority:
    The Oil and Pipelines Agency
    Clive House, 6th Floor, 70 Petty France, Westminster, London, SW1H 9EX, United Kingdom
    Tel. 07891 710312, Email: karen.robinson@oilandpipelines.com, URL: https://gov.uk/opa
    Contact: Karen Robinson, Attn: Karen Robinson
      Sub Type: Design and Execution

4. Description: Pumping station construction work. At present the OFD Loch Striven does not have an F76 fuel filtering system on site and the present pumping system requires the use of the Balance Tank. However, the Balance Tank has been removed from service and decommissioned rendering the existing F76 transfer pumps obsolete.
In order to increase the flexibility of the site, there is a requirement to pump between tanks to allow for the complete inter-tank transfers of certain storage tanks. There is also a future requirement to filter off-specification F-76 fuel to allow re-use.
In addition, there is a requirement to replace the current F-44 pumps, control systems and power feeds.
Power feeds are to be rated IAW with the Depot DSEAR Assessment.

The new pump system and filter system will be composed essentially of following:
•2 x pumps located in the old Boiler House area
•2 x Coalescer Filters (to clean F-76)
•2 x new motors and pumps to replace the current aged F44 system.
•Associated pipework
•Power, control and safety trip systems.
5. CPV Codes:
   45232152 - Pumping station construction work.

6. NUTS Codes :
   UK - UNITED KINGDOM

7. Main Site or Location of Works, Main Place of Delivery or Main Place of Performance: UNITED KINGDOM,
8. Reference Attributed by the Awarding Authority:
9. Estimated Value of Requirement: Category G: 500K to 1M
Currency: GBP
10. Deadline for Expression of Interest: 14/01/2019 12:00:00
11. Address to which they must be sent:
    The Oil and Pipelines Agency
    Clive House, 6th Floor, 70 Petty France, Westminster, London, SW1H 9EX, United Kingdom
    Tel. 07891 710312, Email: karen.robinson@oilandpipelines.com, URL: https://gov.uk/opa
    Contact: Karen Robinson, Attn: Karen Robinson
   
12. Other Information:
Other Information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.Deadline for Expression of interest amended to 14 January, 2019 by midday due to further clarification on design requirement.
To view this notice, please click here:
https://opa.delta-esourcing.com/delta/viewNotice.html?noticeId=360133422

13. Description of Amendment / Addition: Deadline for Expression of interest amended to 14 January, 2019 by midday due to further clarification on design requirement. TKR-20181121-PRO-13591098

Suitable for VCO: No
Procedure Type:OPEN
Period of Work Start date: 04/03/2019
Period of Work End date: 05/08/2019



Complementary Information
Funding:
Is this a Framework Agreement?: no

GB-Loch Striven: Replacement Transfer Pumping Arrangement - OFD Loch Striven - F44 Installation & F76 Strip Out

Competitive Contract Notice Addendum

Associated Parent Notice
CompetitiveContractNotice - GB-Loch Striven: Replacement Transfer Pumping Arrangement - OFD Loch Striven - F44 Installation & F76 Strip Out
1. Title: GB-Loch Striven: Replacement Transfer Pumping Arrangement - OFD Loch Striven - F44 Installation & F76 Strip Out
2. Awarding Authority:
    The Oil and Pipelines Agency
    Clive House, 6th Floor, 70 Petty France, Westminster, London, SW1H 9EX, United Kingdom
    Tel. 07891 710312, Email: karen.robinson@oilandpipelines.com, URL: https://gov.uk/opa
    Contact: Karen Robinson, Attn: Karen Robinson
      Sub Type: Design and Execution

4. Description: Pumping station construction work. At present the OFD Loch Striven does not have an F76 fuel filtering system on site and the present pumping system requires the use of the Balance Tank. However, the Balance Tank has been removed from service and decommissioned rendering the existing F76 transfer pumps obsolete.
In order to increase the flexibility of the site, there is a requirement to pump between tanks to allow for the complete inter-tank transfers of certain storage tanks. There is also a future requirement to filter off-specification F-76 fuel to allow re-use.
In addition, there is a requirement to replace the current F-44 pumps, control systems and power feeds.
Power feeds are to be rated IAW with the Depot DSEAR Assessment.

The new pump system and filter system will be composed essentially of following:
•2 x pumps located in the old Boiler House area
•2 x Coalescer Filters (to clean F-76)
•2 x new motors and pumps to replace the current aged F44 system.
•Associated pipework
•Power, control and safety trip systems.
5. CPV Codes:
   45232152 - Pumping station construction work.

6. NUTS Codes :
   UK - UNITED KINGDOM

7. Main Site or Location of Works, Main Place of Delivery or Main Place of Performance: UNITED KINGDOM,
8. Reference Attributed by the Awarding Authority:
9. Estimated Value of Requirement: Category G: 500K to 1M
Currency: GBP
10. Deadline for Expression of Interest: 28/01/2019 12:00:00
11. Address to which they must be sent:
    The Oil and Pipelines Agency
    Clive House, 6th Floor, 70 Petty France, Westminster, London, SW1H 9EX, United Kingdom
    Tel. 07891 710312, Email: karen.robinson@oilandpipelines.com, URL: https://gov.uk/opa
    Contact: Karen Robinson, Attn: Karen Robinson
   
12. Other Information:
Other Information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.Addendum Notice
To view this notice, please click here:
https://opa.delta-esourcing.com/delta/viewNotice.html?noticeId=366616395

13. Description of Amendment / Addition: The deadline for Expressions of interest have changed due to upgrading the final design following discussions with both the Design Consultants and the Clients. TKR-20181221-PRO-13769715

Suitable for VCO: No
Procedure Type:OPEN
Period of Work Start date: 04/03/2019
Period of Work End date: 05/08/2019



Complementary Information
Funding:
Is this a Framework Agreement?: no

GB-Loch Striven: Replacement Transfer Pumping Arrangement - OFD Loch Striven - F44 Installation & F76 Strip Out

Competitive Contract Notice Addendum

Associated Parent Notice
CompetitiveContractNotice - GB-Loch Striven: Replacement Transfer Pumping Arrangement - OFD Loch Striven - F44 Installation & F76 Strip Out
1. Title: GB-Loch Striven: Replacement Transfer Pumping Arrangement - OFD Loch Striven - F44 Installation & F76 Strip Out
2. Awarding Authority:
    The Oil and Pipelines Agency
    Clive House, 6th Floor, 70 Petty France, Westminster, London, SW1H 9EX, United Kingdom
    Tel. 07891 710312, Email: karen.robinson@oilandpipelines.com, URL: https://gov.uk/opa
    Contact: Karen Robinson, Attn: Karen Robinson
      Sub Type: Design and Execution

4. Description: Pumping station construction work. At present the OFD Loch Striven does not have an F76 fuel filtering system on site and the present pumping system requires the use of the Balance Tank. However, the Balance Tank has been removed from service and decommissioned rendering the existing F76 transfer pumps obsolete.
In order to increase the flexibility of the site, there is a requirement to pump between tanks to allow for the complete inter-tank transfers of certain storage tanks. There is also a future requirement to filter off-specification F-76 fuel to allow re-use.
In addition, there is a requirement to replace the current F-44 pumps, control systems and power feeds.
Power feeds are to be rated IAW with the Depot DSEAR Assessment.

The new pump system and filter system will be composed essentially of following:
•2 x pumps located in the old Boiler House area
•2 x Coalescer Filters (to clean F-76)
•2 x new motors and pumps to replace the current aged F44 system.
•Associated pipework
•Power, control and safety trip systems.
5. CPV Codes:
   45232152 - Pumping station construction work.

6. NUTS Codes :
   UK - UNITED KINGDOM

7. Main Site or Location of Works, Main Place of Delivery or Main Place of Performance: UNITED KINGDOM,
8. Reference Attributed by the Awarding Authority:
9. Estimated Value of Requirement: Category G: 500K to 1M
Currency: GBP
10. Deadline for Expression of Interest: 02/03/2019 12:00:00
11. Address to which they must be sent:
   Not Provided
   
12. Other Information:
Other Information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement.
To view this notice, please click here:
https://opa.delta-esourcing.com/delta/viewNotice.html?noticeId=380648486

13. Description of Amendment / Addition: This tender process has been withdrawn to revisit the design and project requirements. TKR-201931-PRO-14200372

Suitable for VCO: No
Procedure Type:OPEN
Period of Work Start date: 04/03/2019
Period of Work End date: 05/08/2019



Complementary Information
Funding:
Is this a Framework Agreement?: no

View Award Notice